Question 41
It is necessary to carry out a feasibility study as _____?
Feasibility study is needed because technology may not be mature enough.
Not clear enough?
Question 42
Feasibility study is carried out by _____?
Feasibility study is carried out by the system analyst with managers.
Not clear enough?
Question 43
The phase of system development associated with creation of the test data is _____?
Test data creation is associated with system acceptance phase.
Not clear enough?
Question 44
Which of the following is a true statement regarding the SDLC phases?
SDLC is often not iterative; traditionally it follows a sequential flow.
Not clear enough?
Question 45
Which step of SDLC performs cost and benefit analysis?
Cost and benefit analysis is done during feasibility study.
Not clear enough?
Question 46
Which of the following is the most important phase of SDLC?
Requirement analysis is the most important phase of SDLC.
Not clear enough?
Question 47
In the first phase of the system development life cycle, which of the following aspects are usually analyzed?
Inputs, outputs, and controls are analyzed in the first phase.
Not clear enough?
Question 48
Which one is not considered during technical feasibility?
Human resource availability is not part of technical feasibility.
Not clear enough?
Question 49
Which phase of the SDLC is known as the "ongoing phase" where the system is periodically evaluated and updated as needed?
System maintenance is the ongoing phase where updates and evaluation occur.
Not clear enough?
Question 50
The final step of the system analysis phase in the SDLC is to _____?
The final step is to write the system analysis report.