Question 1
A can do a piece of work in 4 hours; B and C can do it in 3 hours. A and C can do it in 2 hours. How long will B alone take to do it ?
Let's denote the rate of work for each person. The rate is the amount of work they can complete per hour.
- Let \( R_A \), \( R_B \), and \( R_C \) be the rates of work for A, B, and C, respectively.
Given information:
1. A can do the work in 4 hours, so \( R_A = \dfrac{1}{4} \) (A's rate is one-fourth of the work per hour).
2. B and C can do the work in 3 hours, so \( R_B + R_C = \dfrac{1}{3} \) (the combined rate of B and C is one-third of the work per hour).
3. A and C can do the work in 2 hours, so \( R_A + R_C = \dfrac{1}{2} \) (the combined rate of A and C is one-half of the work per hour).
Now, let's set up and solve the equations:
Equation 1: \( R_A = \dfrac{1}{4} \)
Equation 2: \( R_B + R_C = \dfrac{1}{3} \)
Equation 3: \( R_A + R_C = \dfrac{1}{2} \)
Now, substitute Equation 1 into Equation 3:\[ \dfrac{1}{4} + R_C = \dfrac{1}{2} \]\[ R_C = \dfrac{1}{2} - \dfrac{1}{4} \]\[ R_C = \dfrac{1}{4} \]
Now, substitute \( R_C \) into Equation 2:\[ R_B + \dfrac{1}{4} = \dfrac{1}{3} \]\[ R_B = \dfrac{1}{3} - \dfrac{1}{4} \]\[ R_B = \dfrac{1}{12} \]
Now, we know \( R_B \), which is the rate at which B works. To find the time \( T \) B alone will take to do the work, we use the formula:\[ T = \dfrac{\text{Total work}}{\text{Rate of B}} \]\[ T = \dfrac{1}{R_B} \]
Substitute the value of \( R_B \):\[ T = \dfrac{1}{\dfrac{1}{12}} \]\[ T = 12 \]
Therefore, B alone will take 12 hours to do the work. Hence, the correct answer is 12 hours.
Not clear enough?
Question 2
If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many days can A alone complete the work ?
Let's denote the rates of work for A and B as \( R_A \) and \( R_B \) respectively.
Given information:
1. A and B together can complete the work in 15 days, so their combined rate is \( R_A + R_B = \dfrac{1}{15} \) (the work completed per day by A and B combined is one-fifteenth of the total work).
2. B alone can complete the work in 20 days, so \( R_B = \dfrac{1}{20} \) (the work completed per day by B alone is one-twentieth of the total work).
Now, let's set up and solve the equations:
Equation 1: \( R_A + R_B = \dfrac{1}{15} \)
Equation 2: \( R_B = \dfrac{1}{20} \)
Now, substitute Equation 2 into Equation 1:\[ R_A + \dfrac{1}{20} = \dfrac{1}{15} \]\[ R_A = \dfrac{1}{15} - \dfrac{1}{20} \]\[ R_A = \dfrac{1}{60} \]
Now, we know \( R_A \), which is the rate at which A works. To find the time \( T \) A alone will take to do the work, we use the formula:\[ T = \dfrac{\text{Total work}}{\text{Rate of A}} \]\[ T = \dfrac{1}{R_A} \]
Substitute the value of \( R_A \):\[ T = \dfrac{1}{\dfrac{1}{60}} \]\[ T = 60 \]
Therefore, A alone will take 60 days to complete the work. Hence, the correct answer is 60 days.
Not clear enough?
Question 3
A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in ?
Let \( R_A \) be the rate of work for A, and \( R_B \) be the rate of work for B.
Given information:
1. A and B together can complete the work in 12 days, so their combined rate is \( R_A + R_B = \dfrac{1}{12} \).
2. B alone can complete the work in 30 days, so \( R_B = \dfrac{1}{30} \).
Now, let's set up and solve the equations:
Equation 1: \( R_A + R_B = \dfrac{1}{12} \)
Equation 2: \( R_B = \dfrac{1}{30} \)
Now, substitute Equation 2 into Equation 1:\[ R_A + \dfrac{1}{30} = \dfrac{1}{12} \]\[ R_A = \dfrac{1}{12} - \dfrac{1}{30} \]\[ R_A = \dfrac{1}{20} \]
Now, we know \( R_A \), which is the rate at which A works. To find the time \( T \) A alone will take to do the work, we use the formula:\[ T = \dfrac{\text{Total work}}{\text{Rate of A}} \]\[ T = \dfrac{1}{R_A} \]
Substitute the value of \( R_A \):\[ T = \dfrac{1}{\dfrac{1}{20}} \]\[ T = 20 \]
Therefore, A alone will take 20 days to complete the work. Hence, the correct answer is 20 days.
Not clear enough?
Question 4
If A and B together can complete a work in 18 days, A and C together in 12 days and B and C together in 9 days, then B alone can do the work in ?
Consider the given information about the time it takes for different pairs of workers to complete a task:
1. (A + B) together can complete the work in 18 days.
2. (B + C) together can complete the work in 9 days.
3. (C + A) together can complete the work in 12 days.
Let's calculate the one-day work rates for each pair:
- The one-day work rate of (A + B) is \( \dfrac{1}{18} \) (equation 1).
- The one-day work rate of (B + C) is \( \dfrac{1}{9} \) (equation 2).
- The one-day work rate of (C + A) is \( \dfrac{1}{12} \) (equation 3).
Now, by adding equations (1), (2), and (3), we find the combined one-day work rate of 2(A + B + C):
\[ \text{One-day work rate of 2(A + B + C)} = \left(\dfrac{1}{18}\right) + \left(\dfrac{1}{9}\right) + \left(\dfrac{1}{12}\right) \]
Simplifying the expression, we get:
\[ \text{One-day work rate of 2(A + B + C)} = \dfrac{2 + 4 + 3}{36} \]
Further simplification yields:
\[ \text{One-day work rate of 2(A + B + C)} = \dfrac{9}{36} \]
Now, we find the one-day work rate of (A + B + C):
\[ \text{One-day work rate of (A + B + C)} = \dfrac{1}{8} \] (equation 4).
By subtracting equation (3) from equation (4), we determine the one-day work rate of B:
\[ \text{One-day work rate of B} = \dfrac{1}{8} - \dfrac{1}{12} \]
This simplifies to:
\[ \text{One-day work rate of B} = \dfrac{3 - 2}{24} = \dfrac{1}{24} \]
In conclusion, the one-day work rate of B is \( \dfrac{1}{24} \), and to find the time B alone will take to complete the work, we use the formula:
\[ \text{Time (B alone)} = \dfrac{1}{\text{One-day work rate of B}} = \dfrac{1}{\dfrac{1}{24}} = 24 \]
Hence, B alone can complete the work in 24 days.
Not clear enough?
Question 5
A and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. C alone can do the work in ?
Let's denote the work rates of A, B, and C as \(A_r\), \(B_r\), and \(C_r\) respectively. Also, let \(T\) be the total amount of work.
The given information can be translated into equations:
1. A and B together can complete the work in 10 days:
\[\dfrac{T}{A_r + B_r} = 10\]
2. B and C together can complete the work in 15 days:
\[\dfrac{T}{B_r + C_r} = 15\]
3. C and A together can complete the work in 20 days:
\[\dfrac{T}{C_r + A_r} = 20\]
Now, let's solve these equations. Combining equations 1, 2, and 3, we get:
\[A_r + B_r = \dfrac{T}{10}\]\[B_r + C_r = \dfrac{T}{15}\]\[C_r + A_r = \dfrac{T}{20}\]
Adding all three equations gives:\[2(A_r + B_r + C_r) = \dfrac{T}{10} + \dfrac{T}{15} + \dfrac{T}{20}\]
Simplifying the right side:\[2(A_r + B_r + C_r) = \dfrac{3T + 2T + T}{60}\]\[2(A_r + B_r + C_r) = \dfrac{6T}{60}\]\[A_r + B_r + C_r = \dfrac{T}{10}\]
Now, substitute this back into any of the original equations, let's use equation 1:\[\dfrac{T}{\dfrac{T}{10}} = 10\]\[T = 10\]
Now, we can find the rate at which C alone can do the work:\[C_r = \dfrac{T}{20} = \dfrac{10}{20} = \dfrac{1}{2}\]
So, C alone can complete the work in \(2 \times \text{days} = 2 \times 60 = 120\) days.
Therefore, the correct answer is 120 days.
Not clear enough?
Question 6
A and B can do a piece of work in 72 days. B and C can do it in 120 days, A and C can do it in 90 days. In how many days all the three together can do the work ?
Let's denote the efficiency of A, B, and C as \(a\), \(b\), and \(c\) respectively. The given information can be expressed as the following three equations:
1. \(A + B = \dfrac{1}{72}\) (A and B can do the work in 72 days)
2. \(B + C = \dfrac{1}{120}\) (B and C can do the work in 120 days)
3. \(A + C = \dfrac{1}{90}\) (A and C can do the work in 90 days)
Now, we need to find \(A + B + C\) which represents the combined efficiency of all three working together.
Adding the three equations above:
\[A + B + B + C + A + C = \dfrac{1}{72} + \dfrac{1}{120} + \dfrac{1}{90}\]
Combining like terms:
\[2A + 2B + 2C = \dfrac{5 + 3 + 4}{360}\]
\[2(A + B + C) = \dfrac{12}{360}\]
\[A + B + C = \dfrac{6}{360}\]
\[A + B + C = \dfrac{1}{60}\]
So, all three together can do the work in 60 days. Therefore, the correct answer is:
\[\text{60 days}\]
Not clear enough?
Question 7
8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed ?
Let's denote the rate of work of one man as \( M \) (i.e., the amount of work one man can do in one day).
The total work \( W \) is given by the product of the number of men and the number of days:
\[ W = \text{Number of men} \times \text{Number of days} \times \text{Rate of work per man} \]
Given that 8 men can do the work in 12 days, we can write the equation as:
\[ W = 8 \times 12 \times M \]
Now, after 6 days of work, the work completed by 8 men is \( 8 \times 6 \times M \). The remaining work to be done is \( W - 8 \times 6 \times M \).
Then, 4 more men join, making the total number of men \( (8 + 4) = 12 \). Let \( D \) be the number of days needed to complete the remaining work with 12 men.
So, the equation becomes:
\[ W - 8 \times 6 \times M = 12 \times D \times M \]
Now, we can substitute the value of \( W \) from the first equation:
\[ 8 \times 12 \times M - 8 \times 6 \times M = 12 \times D \times M \]
Solving for \( D \):
\[ 96 - 48 = 12D \]
\[ 48 = 12D \]
\[ D = 4 \]
Therefore, the remaining work would be completed in 4 days. Hence, the correct answer is:
\[ \text{4 days} \]
Not clear enough?
Question 8
A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last ?
Let's find the rate at which A and B work individually.
The work rate of A is \( \dfrac{1}{20} \) (because A can complete the work in 20 days).
The work rate of B is \( \dfrac{1}{12} \) (because B can complete the work in 12 days).
When A started working alone for 4 days, the amount of work completed by A alone is \( 4 \times \dfrac{1}{20} = \dfrac{1}{5} \).
Now, the remaining work to be done when B joins is \( 1 - \dfrac{1}{5} = \dfrac{4}{5} \).
Now, A and B work together. The combined rate of A and B is \( \dfrac{1}{20} + \dfrac{1}{12} \).
Let \( t \) be the time (in days) B works with A. So, the equation representing the remaining work is:
\[ t \times \left(\dfrac{1}{20} + \dfrac{1}{12}\right) = \dfrac{4}{5} \]
Combine the fractions and solve for \( t \):
\[ t \times \left(\dfrac{6 + 10}{120}\right) = \dfrac{4}{5} \]
\[ t \times \left(\dfrac{16}{120}\right) = \dfrac{4}{5} \]
\[ t \times \left(\dfrac{4}{30}\right) = \dfrac{4}{5} \]
\[ t \times \left(\dfrac{2}{15}\right) = \dfrac{4}{5} \]
\[ t = \dfrac{4}{5} \div \dfrac{2}{15} \]
\[ t = \dfrac{4}{5} \times \dfrac{15}{2} \]
\[ t = 6 \]
So, B works with A for 6 days. A worked alone for 4 days before that. Therefore, the total time the work lasted is \( 4 + 6 = 10 \) days.
Hence, the correct answer is:
\[ \text{10 days} \]
Not clear enough?
Question 9
5 men can do a piece of work in 6 days while 10 women can do it in 5 days. In how many days can 5 women and 3 men do it ?
Let's find the rates of work for both men and women first.
The work rate of 5 men is \( \dfrac{1}{6} \) (because 5 men can complete the work in 6 days).
The work rate of 10 women is \( \dfrac{1}{5} \) (because 10 women can complete the work in 5 days).
Now, we can find the rates for men and women individually:
1 man's rate = \( \dfrac{1}{6 \times 5} = \dfrac{1}{30} \)
1 woman's rate = \( \dfrac{1}{10 \times 5} = \dfrac{1}{50} \)
Now, let \( t \) be the number of days it takes for 5 women and 3 men to complete the work together. The combined rate of 5 women and 3 men is \( 5 \times \dfrac{1}{50} + 3 \times \dfrac{1}{30} \).
The equation representing the work completed is:
\[ t \times \left(5 \times \dfrac{1}{50} + 3 \times \dfrac{1}{30}\right) = 1 \]
Combine the fractions and solve for \( t \):
\[ t \times \left(\dfrac{1}{10} + \dfrac{1}{10}\right) = 1 \]
\[ t \times \left(\dfrac{2}{10}\right) = 1 \]
\[ t \times \left(\dfrac{1}{5}\right) = 1 \]
\[ t = 5 \]
So, 5 women and 3 men can complete the work together in 5 days.
Hence, the correct answer is:
\[ \text{5 days} \]
Not clear enough?
Question 10
4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it ?
Let's denote the rate of work for one man as \(M\) and for one woman as \(W\).
The work rate of 4 men and 6 women is \(4M + 6W\), and the work rate of 3 men and 7 women is \(3M + 7W\).
The information can be expressed in terms of rates and time:
1. \( (4M + 6W) \times 8 = 1 \) (because they complete the work in 8 days)
2. \( (3M + 7W) \times 10 = 1 \) (because they complete the work in 10 days)
Now, let's solve these two equations to find the values of \(M\) and \(W\).
From equation (1):
\[ 32M + 48W = 1 \]
From equation (2):
\[ 30M + 70W = 1 \]
Now, we can solve these two equations simultaneously. One way to do this is by subtracting equation (2) from equation (1):
\[ (32M + 48W) - (30M + 70W) = 1 - 1 \]
\[ 2M - 22W = 0 \]
\[ 2M = 22W \]
\[ M = 11W \]
Now, let's substitute this back into equation (1):
\[ 32(11W) + 48W = 1 \]
\[ 352W + 48W = 1 \]
\[ 400W = 1 \]
\[ W = \dfrac{1}{400} \]
Now, we want to find how many days 10 women will take to complete the work. The rate of 10 women is \(10 \times \dfrac{1}{400} = \dfrac{1}{40}\).
Let \(D\) be the number of days:
\[ D \times \dfrac{1}{40} = 1 \]
\[ D = 40 \]
So, 10 women will take 40 days to complete the work.
Hence, the correct answer is:
\[ \text{40 days} \]
Not clear enough?