Question 31
If x can finish a job in 4 hours and y can finish the same job in 8 hours independently, then they together will finish the job in ?
To find out how long it takes for x and y to finish the job together, we need to calculate their combined work rate.
Let's denote the work rate of x as \(X_{\text{rate}}\) and the work rate of y as \(Y_{\text{rate}}\).
If x can finish a job in 4 hours, his work rate is:\[X_{\text{rate}} = \dfrac{1}{4}\text{ job per hour}\]
Similarly, if y can finish the job in 8 hours, his work rate is:\[Y_{\text{rate}} = \dfrac{1}{8}\text{ job per hour}\]
When they work together, their combined work rate is the sum of their individual work rates:
\[\text{Combined rate} = X_{\text{rate}} + Y_{\text{rate}}\]\[\text{Combined rate} = \dfrac{1}{4} + \dfrac{1}{8}\]
\[\text{Combined rate} = \dfrac{2}{8} + \dfrac{1}{8}\]\[\text{Combined rate} = \dfrac{3}{8}\text{ job per hour}\]
Now, to find out how many hours it takes for them to finish the job together, we use the formula:
\[\text{Time} = \dfrac{\text{Total work}}{\text{Combined rate}}\]
Since the total work is 1 (the entire job), as they complete the entire piece of work:
\[\text{Time} = \dfrac{1}{\dfrac{3}{8}}\]
\[\text{Time} = \dfrac{8}{3}\]
\[\text{Time} = 2 \dfrac{2}{3}\text{ hours}\]
Since we're asked for the answer in minutes:
\[2 \dfrac{2}{3} \text{ hours} = 2 \times 60 + \dfrac{2}{3} \times 60 \text{ minutes}\]\[= 120 + 40\]\[= 160\text{ minutes}\]
So, x and y will finish the job together in \(\boxed{160}\) minutes.
Not clear enough?
Question 32
If 3 men or 4 women can plough a field in 43 days, how long will 7 men and 5 women take to plough it ?
Let's first find the work rate of a man and a woman separately.
If 3 men can plow a field in 43 days, then the work rate of one man is:\[ \text{Rate of one man} = \dfrac{1}{3 \times 43} = \dfrac{1}{129} \text{ per day} \]
Similarly, if 4 women can plow the same field in 43 days, then the work rate of one woman is:\[ \text{Rate of one woman} = \dfrac{1}{4 \times 43} = \dfrac{1}{172} \text{ per day} \]
Now, we need to find how much work 7 men and 5 women can do in one day together.
The combined work rate of 7 men and 5 women is:\[ \text{Combined rate} = 7 \times \text{Rate of one man} + 5 \times \text{Rate of one woman} \]\[ \text{Combined rate} = 7 \times \dfrac{1}{129} + 5 \times \dfrac{1}{172} \]\[ \text{Combined rate} = \dfrac{7}{129} + \dfrac{5}{172} \]
Now, let's find a common denominator for the fractions:
\[ \text{Combined rate} = \dfrac{7 \times 172}{129 \times 172} + \dfrac{5 \times 129}{129 \times 172} \]\[ \text{Combined rate} = \dfrac{1204}{22188} + \dfrac{645}{22188} \]\[ \text{Combined rate} = \dfrac{1849}{22188} \]
Now, we can calculate how many days it will take for them to plow the field:
\[ \text{Days required} = \dfrac{1}{\text{Combined rate}} = \dfrac{22188}{1849} \]
\[ \text{Days required} = 12 \]
Therefore, 7 men and 5 women together will take \(\boxed{12}\) days to plow the field.
Not clear enough?
Question 33
x does 1/4 of a job in 6 days. y completes rest of the job in 12 days. Then x and y could complete the job together in ?
Let's first find out the work rate of x and y individually.
If x completes \( \dfrac{1}{4} \) of the job in 6 days, his work rate is:\[ x_{\text{rate}} = \dfrac{\dfrac{1}{4}}{6} = \dfrac{1}{24} \]
Now, since y completes the rest of the job in 12 days, and \( \dfrac{3}{4} \) of the job is left for y, his work rate is:\[ y_{\text{rate}} = \dfrac{\dfrac{3}{4}}{12} = \dfrac{1}{16} \]
Now, when they work together, their combined work rate is the sum of their individual work rates:
\[ \text{Combined rate} = x_{\text{rate}} + y_{\text{rate}} = \dfrac{1}{24} + \dfrac{1}{16} \]
\[ \text{Combined rate} = \dfrac{1}{24} + \dfrac{3}{48} \]
\[ \text{Combined rate} = \dfrac{2 + 3}{48} \]
\[ \text{Combined rate} = \dfrac{5}{48} \]
Now, let's find how long it will take for them to complete the job together:
\[ \text{Time} = \dfrac{\text{Total work}}{\text{Combined rate}} \]
Since the total work is 1 (the entire job):
\[ \text{Time} = \dfrac{1}{\dfrac{5}{48}} \]
\[ \text{Time} = \dfrac{48}{5} \]
\[ \text{Time} = 9 \dfrac{3}{5} \text{ days} \]
Therefore, x and y could complete the job together in \(\boxed{9 \dfrac{3}{5}}\) days.
Not clear enough?
Question 34
A and B can do a piece of work in 10 days. B and C can do it in 12 days. C and A in 15 days. In how many days will C finish it alone ?
Let's denote the individual rates of work for A, B, and C as \(A_r\), \(B_r\), and \(C_r\) respectively.
From the given information, we can form the following equations:
1. The combined work rate of A and B is \(A_r + B_r = \dfrac{1}{10}\).
2. The combined work rate of B and C is \(B_r + C_r = \dfrac{1}{12}\).
3. The combined work rate of C and A is \(C_r + A_r = \dfrac{1}{15}\).
We're asked to find the rate at which C works alone, denoted as \(C_r\).
Now, let's add equations 1, 2, and 3:
\[ (A_r + B_r) + (B_r + C_r) + (C_r + A_r) = \dfrac{1}{10} + \dfrac{1}{12} + \dfrac{1}{15} \]
\[ 2(A_r + B_r + C_r) = \dfrac{6 + 5 + 4}{60} \]
\[ 2(A_r + B_r + C_r) = \dfrac{15}{60} \]
\[ A_r + B_r + C_r = \dfrac{15}{120} \]
\[ A_r + B_r + C_r = \dfrac{1}{8} \]
Now, since A and B can do the work in 10 days together, their combined work rate is \( \dfrac{1}{10} \). Similarly, we find \(A_r + B_r + C_r = \dfrac{1}{8}\). This means \(C_r = \dfrac{1}{8} - \dfrac{1}{10} = \dfrac{5}{40} - \dfrac{4}{40} = \dfrac{1}{40}\).
This implies that C can finish the work alone in 40 days.
Therefore, C will finish the work alone in \(\boxed{40}\) days.
Not clear enough?
Question 35
A and B can complete a piece of work in 8 days, B and C can do it in 12 days, C and A can do it in 8 days. A, B and C together can complete it in ?
Let's denote the individual rates of work for A, B, and C as \(A_r\), \(B_r\), and \(C_r\) respectively.
From the given information, we can form the following equations:
1. The combined work rate of A and B is \(A_r + B_r = \dfrac{1}{8}\).
2. The combined work rate of B and C is \(B_r + C_r = \dfrac{1}{12}\).
3. The combined work rate of C and A is \(C_r + A_r = \dfrac{1}{8}\).
We're asked to find the combined work rate of A, B, and C together, denoted as \(A_r + B_r + C_r\).
Now, let's add equations 1, 2, and 3:
\[ (A_r + B_r) + (B_r + C_r) + (C_r + A_r) = \dfrac{1}{8} + \dfrac{1}{12} + \dfrac{1}{8} \]
\[ 2(A_r + B_r + C_r) = \dfrac{3 + 2 + 3}{24} \]
\[ 2(A_r + B_r + C_r) = \dfrac{8}{24} \]
\[ A_r + B_r + C_r = \dfrac{8}{48} \]
\[ A_r + B_r + C_r = \dfrac{1}{6} \]
Therefore, A, B, and C together can complete the work in \(\boxed{6}\) days.
Not clear enough?
Question 36
A, B and C together can complete a piece of work in 30 minutes. A and B together can complete the same work in 50 minutes. C alone can complete the work in ?
Let's denote the individual rates of work for A, B, and C as \(A_r\), \(B_r\), and \(C_r\) respectively.
From the given information, we can form the following equations:
1. The combined work rate of A, B, and C is \(A_r + B_r + C_r = \dfrac{1}{30}\).
2. The combined work rate of A and B is \(A_r + B_r = \dfrac{1}{50}\).
We're asked to find the work rate of C alone, denoted as \(C_r\).
Now, let's subtract equation 2 from equation 1 to find \(C_r\):
\[ (A_r + B_r + C_r) - (A_r + B_r) = \dfrac{1}{30} - \dfrac{1}{50} \]
\[ C_r = \dfrac{1}{30} - \dfrac{1}{50} \]
\[ C_r = \dfrac{5}{150} - \dfrac{3}{150} \]
\[ C_r = \dfrac{2}{150} \]
\[ C_r = \dfrac{1}{75} \]
This means that C can complete \( \dfrac{1}{75} \) of the work in one minute.
Therefore, C alone can complete the work in \(\boxed{75}\) minutes.
Not clear enough?
Question 37
A and B can do a piece of work in 36 days, B and C can do it in 60 days, A and C can do it in 45 days. C alone can do it in ?
Let's denote the rates of work for A, B, and C as \(A_r\), \(B_r\), and \(C_r\) respectively.
From the given information, we can form the following equations:
1. The combined work rate of A and B is \(A_r + B_r = \dfrac{1}{36}\).
2. The combined work rate of B and C is \(B_r + C_r = \dfrac{1}{60}\).
3. The combined work rate of A and C is \(A_r + C_r = \dfrac{1}{45}\).
We're asked to find the rate of work of C alone, denoted as \(C_r\).
Now, let's add equations 1, 2, and 3:
\[ (A_r + B_r) + (B_r + C_r) + (A_r + C_r) = \dfrac{1}{36} + \dfrac{1}{60} + \dfrac{1}{45} \]
\[ 2(A_r + B_r + C_r) = \dfrac{5 + 3 + 4}{180} \]
\[ 2(A_r + B_r + C_r) = \dfrac{12}{180} \]
\[ A_r + B_r + C_r = \dfrac{12}{360} \]
\[ A_r + B_r + C_r = \dfrac{1}{30} \]
We found that \(A_r + B_r + C_r = \dfrac{1}{30}\).
We know that the combined work rate of A, B, and C is \(A_r + B_r + C_r = \dfrac{1}{30}\). We also know that the combined work rate of A and B is \(A_r + B_r = \dfrac{1}{36}\).
Therefore, the work rate of C alone is \(C_r = \dfrac{1}{30} - \dfrac{1}{36}\):
\[ C_r = \dfrac{6}{180} - \dfrac{5}{180} \]
\[ C_r = \dfrac{1}{180} \]
This means that C can complete \( \dfrac{1}{180} \) of the work in one day.
Therefore, C alone can complete the work in \( \boxed{180} \) days.
Not clear enough?
Question 38
A can do a work in 6 days and B in 9 days. How many days will both take together to complete the work ?
To find out how many days it will take for A and B to complete the work together, we need to calculate their combined work rate.
Let's denote the work rate of A as \(A_r\) and the work rate of B as \(B_r\).
If A can do the work in 6 days, his work rate is:\[ A_r = \dfrac{1}{6} \text{ job per day} \]
Similarly, if B can do the work in 9 days, his work rate is:\[ B_r = \dfrac{1}{9} \text{ job per day} \]
When they work together, their combined work rate is the sum of their individual work rates:
\[ \text{Combined rate} = A_r + B_r = \dfrac{1}{6} + \dfrac{1}{9} \]
\[ \text{Combined rate} = \dfrac{3}{18} + \dfrac{2}{18} \]
\[ \text{Combined rate} = \dfrac{5}{18} \text{ job per day} \]
Now, to find out how many days it takes for them to complete the work together, we use the formula:
\[ \text{Time} = \dfrac{\text{Total work}}{\text{Combined rate}} \]
Since the total work is 1 (the entire job):
\[ \text{Time} = \dfrac{1}{\dfrac{5}{18}} \]
\[ \text{Time} = \dfrac{18}{5} \]
\[ \text{Time} = 3.6 \text{ days} \]
Therefore, A and B together will take \(\boxed{3.6}\) days to complete the work.
Not clear enough?
Question 39
A particular job can be completed by a team of 10 men in 12 days. The same job can be completed by a team of 10 women in 6 days. How many days are needed to complete the job if the two teams work together ?
Let's denote the total work as \( W \).
If a team of 10 men can complete the job in 12 days, then the rate of work for one man is:\[ \text{Rate of one man} = \dfrac{W}{\text{Total days} \times \text{Number of men}} = \dfrac{W}{12 \times 10} = \dfrac{W}{120} \]
Similarly, if a team of 10 women can complete the same job in 6 days, then the rate of work for one woman is:\[ \text{Rate of one woman} = \dfrac{W}{\text{Total days} \times \text{Number of women}} = \dfrac{W}{6 \times 10} = \dfrac{W}{60} \]
Now, if the two teams work together, their combined rate of work will be the sum of their individual rates:
\[ \text{Combined rate} = \text{Rate of one man} + \text{Rate of one woman} \]\[ \text{Combined rate} = \dfrac{W}{120} + \dfrac{W}{60} \]
\[ \text{Combined rate} = \dfrac{W}{120} + \dfrac{2W}{120} \]\[ \text{Combined rate} = \dfrac{3W}{120} \]\[ \text{Combined rate} = \dfrac{W}{40} \]
Now, to find out how many days it takes for both teams to complete the work together, we use the formula:
\[ \text{Time} = \dfrac{\text{Total work}}{\text{Combined rate}} \]
Since the total work is \( W \) (the entire job):
\[ \text{Time} = \dfrac{W}{\dfrac{W}{40}} = 40 \]
Therefore, if the two teams work together, they will complete the job in \(\boxed{4}\) days.
Not clear enough?
Question 40
A and B together can complete a piece of work in 72 days, B and C together can complete it in 120 days, and A and C together in 90 days. In what time can A alone complete the work ?
Let's denote the rates of work for A, B, and C as \(A_r\), \(B_r\), and \(C_r\) respectively.
From the given information, we can form the following equations:
1. The combined work rate of A and B is \(A_r + B_r = \dfrac{1}{72}\).
2. The combined work rate of B and C is \(B_r + C_r = \dfrac{1}{120}\).
3. The combined work rate of A and C is \(A_r + C_r = \dfrac{1}{90}\).
We're asked to find the work rate of A alone, denoted as \(A_r\).
Now, let's add equations 1, 2, and 3:
\[ (A_r + B_r) + (B_r + C_r) + (A_r + C_r) = \dfrac{1}{72} + \dfrac{1}{120} + \dfrac{1}{90} \]
\[ 2(A_r + B_r + C_r) = \dfrac{5 + 3 + 4}{360} \]
\[ 2(A_r + B_r + C_r) = \dfrac{12}{360} \]
\[ A_r + B_r + C_r = \dfrac{12}{720} \]
\[ A_r + B_r + C_r = \dfrac{1}{60} \]
Therefore, \(A_r + B_r + C_r = \dfrac{1}{60}\).
We know that the combined work rate of A, B, and C is \(A_r + B_r + C_r = \dfrac{1}{60}\). We also know that the combined work rate of B and C is \(B_r + C_r = \dfrac{1}{120}\).
Therefore, the work rate of A alone is \(A_r = \dfrac{1}{60} - \dfrac{1}{120}\):
\[ A_r = \dfrac{2}{120} - \dfrac{1}{120} \]
\[ A_r = \dfrac{1}{120} \]
This means that A can complete \( \dfrac{1}{120} \) of the work in one day.
Therefore, A alone can complete the work in \( \boxed{120} \) days.
Not clear enough?
You might like
This question is based on General Literary Appreciation.
The old man slept in his favourite chair
The wind ran its fingers through his hair
He looked like a tree gone dry of sap
And his hands were dry upon his lap
The rhyme scheme of the poem above is
A gas at a volume of V\(_0\) in a container at pressure p\(_0\) is compressed to one-fifth of its volume. What will be its pressure if the magnitude of its original temperature T is constant?
Choose the one opposite in meaning to the word(s) underlined. Chief Money-Miss-Road is a sitting duck
The statement in the process of production and distribution of goods, income is generated and distributed amongst the factors of production was given by:
Which of the limited liability companies have a limit of fifty members and do not issues their shares to the public