Question 41

What is the most important criteria in capital budgeting?

Show explanation Expand Question

C. Net present value

Net Present Value (NPV) is the most important criterion in capital budgeting because it measures the expected increase in wealth by considering the time value of money.

Not clear enough?

Question 42

Which of the following statements (in general) is correct?

Show explanation Expand Question

B. The lower the total debt-to-equity ratio, the lower the financial risk for a firm

A lower debt-to-equity ratio indicates the firm relies less on borrowed funds, reducing financial risk and the likelihood of default.

Not clear enough?

Question 43

What should be the focal point of financial management in a firm?

Show explanation Expand Question

C. The creation of value for shareholders

The primary goal of financial management is to maximize shareholder wealth, ensuring decisions increase the value of the firm rather than just focusing on profits or tax minimization.

Not clear enough?

Question 44

What are the two basic types of production systems?

Show explanation Expand Question

B. Intermittent and non-intermittent process

The two basic types of production systems are:

  • Intermittent (or batch) production, where products are made in separate lots.

  • Non-intermittent (or continuous) production, where production runs continuously without interruption.

Not clear enough?

Question 45

What type of process would a paper mill be most likely to use?

Show explanation Expand Question

A. Continuous flow

A paper mill operates using a continuous flow process, where raw materials are processed non-stop to produce large quantities of standardized products.

Not clear enough?

Question 46

What technique deals with the problem of supplying sufficient facilities to production lines or individuals that require uneven service?

Show explanation Expand Question

D. Queuing theory

Queuing theory deals with managing and analyzing waiting lines to ensure sufficient facilities or resources are available for production lines or individuals with uneven demand.

Not clear enough?

Question 47

A manufacturer has been receiving excessive numbers of defective standard machine parts from a vendor on a regular basis. What is the most effective way to design a formal inspection system for incoming parts?

Show explanation Expand Question

C. Statistical quality control

Statistical quality control (SQC) is the most effective method for designing a formal inspection system, as it uses statistical techniques to monitor and control the quality of incoming parts.

Not clear enough?

Question 48

A set of simultaneous equations that has more variables than constraints has

Show explanation Expand Question

B. An infinite number of solutions

A system of simultaneous equations with more variables than constraints is underdetermined, meaning there are infinitely many solutions that satisfy all equations.

Not clear enough?

Question 49

In a PERT/CPM network, computing the critical path requires

Show explanation Expand Question

B. Assigning the earliest finish time for an activity as the earliest start time for the next

In PERT/CPM, the critical path is determined by calculating earliest start and finish times and ensuring that the earliest finish of one activity becomes the earliest start of the next.

Not clear enough?

Question 50

At the completion of the forward and backward passes, the slack for an activity is given by the

Show explanation Expand Question

C. Difference between latest start and early start 

In PERT/CPM, slack (or float) is the amount of time an activity can be delayed without delaying the project. It is calculated as:

Slack = LS - ES = LF - EF

Not clear enough?